First Gen – San Gabriel Combined-Cycle Natural Gas-Fired Power Plant 1311 MW – Batangas
First Gen Corporation (First Gen), through its wholly-owned subsidiary, First NatGas Power Corp., is undertaking the San Gabriel combined-cycle natural gas-fired power plant in the Philippines.The project involves the construction of a natural gas-fired power plant with a capacity of 1,311MW. The project is planned to be implemented in three phases. It includes the construction of substations, and powerhouses, the installation of generators, transformers and turbines, and the laying of transmission lines.First Phase: It includes the construction of a 97MW power plant with a total expenditure of US$150 million. This phase is also called as 'Avion' power plant.Second Phase: It includes the construction of a 414MW power plant with a cost of US$600 million.Third Phase: It includes the construction of an 800MW power plant comprising two units of 400MW each.The project secured environmental approval in 2005.In October 2012, First Gen signed a 10-year loan agreement with Bank of the Philippine Islands, BDO Unibank Inc., Philippine National Bank, Rizal Commercial Banking Corp., Security Bank Corp., The Hong Kong and Shanghai Banking Corp., and Union Bank of the Philippines for the funding of the project.On December 16, 2013, Siemens Group was awarded a turnkey contract of worth US$543 million for the second phase of the project. The project will utilize Siemens’s SGT6-8000H gas turbine technology. Under the terms, Siemens, AG will supply the equipment, will provide engineering, design, procurement and construction services, and also undertake the operation and maintenance of unit for 9.5 years.On January 14, 2014, a groundbreaking ceremony was held on the second phase.In July 2014, First Gen secured US$265 million loan from KfW IPEX-Bank for the second phase of the proposed project.In August 2014, Slovakian firm, Istroenergo Group A.s. (IEG) was appointed as engineering, procurement, and construction (EPC) contractor for the first phase.In April 2016, construction activities on the first and second phase completed.
Scope
The project involves the construction of a natural gas-fired power plant with a capacity of 1,311MW at San Gabriel in Batangas, the Philippines. The US$1,800 million project includes the following:1. Construction of a 97MW power plant under first phase2. Construction of a 414MW power plant under second phase3. Construction of a 2x400MW power plant under third phase
Key Highlights
First Gen Corporation (First Gen), through its wholly-owned subsidiary, First NatGas Power Corp., is undertaking the San Gabriel combined-cycle natural gas-fired power plant in the Philippines.The project involves the construction of a natural gas-fired power plant with a capacity of 1,311MW. The project is planned to be implemented in three phases. It includes the construction of substations, and powerhouses, the installation of generators, transformers and turbines, and the laying of transmission lines.First Phase: It includes the construction of a 97MW power plant with a total expenditure of US$150 million. This phase is also called as 'Avion' power plant.Second Phase: It includes the construction of a 414MW power plant with a cost of US$600 million.Third Phase: It includes the construction of an 800MW power plant comprising two units of 400MW each.The project secured environmental approval in 2005.In October 2012, First Gen signed a 10-year loan agreement with Bank of the Philippine Islands, BDO Unibank Inc., Philippine National Bank, Rizal Commercial Banking Corp., Security Bank Corp., The Hong Kong and Shanghai Banking Corp., and Union Bank of the Philippines for the funding of the project.On December 16, 2013, Siemens Group was awarded a turnkey contract of worth US$543 million for the second phase of the project. The project will utilize Siemens’s SGT6-8000H gas turbine technology. Under the terms, Siemens, AG will supply the equipment, will provide engineering, design, procurement and construction services, and also undertake the operation and maintenance of unit for 9.5 years.On January 14, 2014, a groundbreaking ceremony was held on the second phase.In July 2014, First Gen secured US$265 million loan from KfW IPEX-Bank for the second phase of the proposed project.In August 2014, Slovakian firm, Istroenergo Group A.s. (IEG) was appointed as engineering, procurement, and construction (EPC) contractor for the first phase.In April 2016, construction activities on the first and second phase completed.
Reasons to Buy
First Gen Corporation (First Gen), through its wholly-owned subsidiary, First NatGas Power Corp., is undertaking the San Gabriel combined-cycle natural gas-fired power plant in the Philippines.The project involves the construction of a natural gas-fired power plant with a capacity of 1,311MW. The project is planned to be implemented in three phases. It includes the construction of substations, and powerhouses, the installation of generators, transformers and turbines, and the laying of transmission lines.First Phase: It includes the construction of a 97MW power plant with a total expenditure of US$150 million. This phase is also called as 'Avion' power plant.Second Phase: It includes the construction of a 414MW power plant with a cost of US$600 million.Third Phase: It includes the construction of an 800MW power plant comprising two units of 400MW each.The project secured environmental approval in 2005.In October 2012, First Gen signed a 10-year loan agreement with Bank of the Philippine Islands, BDO Unibank Inc., Philippine National Bank, Rizal Commercial Banking Corp., Security Bank Corp., The Hong Kong and Shanghai Banking Corp., and Union Bank of the Philippines for the funding of the project.On December 16, 2013, Siemens Group was awarded a turnkey contract of worth US$543 million for the second phase of the project. The project will utilize Siemens’s SGT6-8000H gas turbine technology. Under the terms, Siemens, AG will supply the equipment, will provide engineering, design, procurement and construction services, and also undertake the operation and maintenance of unit for 9.5 years.On January 14, 2014, a groundbreaking ceremony was held on the second phase.In July 2014, First Gen secured US$265 million loan from KfW IPEX-Bank for the second phase of the proposed project.In August 2014, Slovakian firm, Istroenergo Group A.s. (IEG) was appointed as engineering, procurement, and construction (EPC) contractor for the first phase.In April 2016, construction activities on the first and second phase completed.
Key Players
Table of Contents
List of Tables
List of Figures
Get in touch to find out about our multi-purchase discounts
reportstore@globaldata.com
Tel +44 (0) 20 7947 2960
Every customer’s requirement is unique. We understand that and can customize the report basis your exact research requirements pertaining to market insights, innovation insights, strategy and planning, and competitive intelligence. You can also avail the option of purchasing stand-alone sections of the report or request for a country specific report.
Still undecided about purchasing this report?
Testimonial
“The GlobalData platform is our go-to tool for intelligence services. GlobalData provides an easy way to access comprehensive intelligence data around multiple sectors, which essentially makes it a one-for-all intelligence platform, for tendering and approaching customers.
GlobalData is very customer orientated, with a high degree of personalised services, which benefits everyday use. The highly detailed project intelligence and forecast reports can be utilised across multiple departments and workflow scopes, from operational to strategic level, and often support strategic decisions. GlobalData Analytics and visualisation solutions has contributed positively when preparing management presentations and strategic papers.”
“COVID-19 has caused significant interference to our business and the COVID-19 intelligence from GlobalData has helped us reach better decisions around strategy. These two highlights have helped enormously to understand the projections into the future concerning our business units, we also utilise the project database to source new projects for Liebherr-Werk to use as an additional source to pitch for new business.”
Your daily news has saved me a lot of time and keeps me up-to-date with what is happening in the market, I like that you almost always have a link to the source origin. We also use your market data in our Strategic Business Process to support our business decisions. By having everything in one place on the Intelligence Center it has saved me a lot of time versus looking on different sources, the alert function also helps with this.
Having used several other market research companies, I find that GlobalData manages to provide that ‘difficult-to-get’ market data that others can’t, as well as very diverse and complete consumer surveys.
Related reports
View more Construction reports